Starting on or about April 17th, A detour will be implemented for construction of Phase 1 of the new roundabout being installed at the intersection of Auburn Road, High Hill Road and Bridgeport Avenue.
Phase 1 will last approximately 16 weeks and will include a detours as follows. High Hill Road (beginning at Tonwship Line Road) and the southern section of Auburn Road (to Center Square Road) will be closed. Vehicles will be detoured down Kings Highway and Center Square Road.
When Phase 1 is complete (approximately 16 weeks), Phase 2 will begin and will be in place until October (more information on Phase 2 detours at that time.)
All businesses will remain open and be accessible during this time.
Construction of the new roundabout is anticipated to be complete in October, weather permitting.